Camps Viaduct improvement work
Camps Viaduct improvement work
A £6 million investment to improve Camps Viaduct.
A £6 million investment to improve Camps Viaduct rail bridge near Motherwell.
From March 2023 to April 2024, Network Rail and our supply chain partner Story begin work to refurbish Camps Viaduct.
Camps Viaduct is around 160 years old, towers 35m above the River Clyde between Ferniegair and Motherwell and serves passengers travelling between Glasgow and Motherwell.
The project will see our teams carrying out essential repairs to extend the lifespan of the structure as part of Network Rail’s commitment to running a safe and reliable railway.
We'll be removing the old paint and rust before carrying out vital metalwork repair work and then priming and re-painting the bridge.
Project Timeline
Project Updates
-
We're on site
Our teams have been on site, doing vital preparation work ahead of our £6 million project to strengthen the rail bridge.
Camscaff laydown area prepared. A laydown area has been prepared for our materials.
You may have been some fencing being put up as we’ve created a pedestrian route to make sure everyone keeps safe.
Pedestrian safe walk route complete with post and wire fencing installed And we’ve started putting scaffolding up on span five of the 35m structure which towers above the River Clyde between Ferniegair and Motherwell, serving passengers travelling by train between Glasgow and Motherwell.
Span 5 scaffold erection underway -
Scaling the scoffold
Our scaffold continues to grow along this tremendous structure.
Our contractors, Camscaff, have already used 96 tonnes of scaffolding, 9000 fittings, 750m of alloy beams and 500m of boards.
Far below the railway, underwater at the bottom of the structure, we’ve begun repairing masonry on three of the piers. 🤿👷
Before we begin strengthening and repainting work, we’re grit blasting it to remove old paintwork. This’ll continue overnight at the weekends. Live nearby? We’ve written to you to share more info, including our working hours.
-
A visit to site
Christina and Steven took some time out to provide an update.
Here they are talking about the progress so far, and the next stages of work.
People living near the structure should receive a letter soon, highlighting shift times and activities planned for the coming weeks as work progresses from the Hamilton side of the structure, over to Motherwell.
-
September progress update
If you live near or have passed the viaduct, you may have seen we've begun erecting scaffolding on span 1 of the viaduct, as work progresses towards the Motherwell side of the structure.
Camps Viaduct - week 24 - scaffold erected on Span 1 Here is some of the work you won't have been able to see - starting with the installation of Cordex sheets to seal and protect Span 2 deck floor.
Stripe coating to Span 8 main girder steel structure. This is done in preparation for mid-coat application.
Once that's complete, the steel will have top coat applied, just like what we've already carried out on Span 11.
Why?
The work is designed to protect and extend the lifespan of the bridge. It's part of a wider, rolling programme of maintenance aimed at keeping the network safe and reliable.
When complete, the works carried out will mean the bridge is stronger, meets current safety standards and will not require repainting for up to two decades.
What will change?
We’re investing £6 million on carrying out essential steelwork repair work before removing the old paint and rust and then priming and re-painting the bridge.
This will address the breakdown of general paintwork and other issues throughout the structure.