Search

Clyde Viaduct Improvement Works

Clyde Viaduct Improvement Works

We’re investing £4.7M to carry out essential repairs to the Clyde Viaduct, including waterproofing to the viaduct deck before removing and replacing sections of steel on the underside of the bridge.

In February 2022, Network Rail commenced a programme of work to refurbish the Clyde Viaduct.

We’re investing £4.7M to carry out essential repairs to the viaduct, including waterproofing the viaduct deck before removing and replacing sections of steel on the underside of the bridge.

The programme is designed to extend the lifespan of the viaduct as part of our commitment to running a safe and reliable railway and is expected to be completed in December 2022.

Project Timeline

  1. February 2022: Work commenced
  2. March 2022: Argyle Line closure allowed 24 hour working as part of wider investment programme
  3. June/July 2022: Completion of the scaffolding is programmed for the end of June.
  4. Mid July 2022: Works to the masonry spans on the North side of the river (Clyde walkway) are programmed, between early and mid July.
  5. December 2022: Project due to be nearing completion

Project Updates

  • Arglye Line closure enabled our teams to work around-the-clock

    Contractor Story Contracting Ltd., engaged by Network Rail, to complete essential work during an intensive 8-week blockade at Clyde Viaduct on Glasgow’s busy Argyle line.

    The line closed on 13th March to allow the team to implement 24-hour working to remove and replace the track and waterproof the bridge deck, with 12,300 working hours completed during the blockade.

    This work was part of a wider £32m investment programme to repair and renew the tunnels, bridges and tracks between Rutherglen and Exhibition Centre.

    It was the most significant piece of engineering on the line in a generation and was all designed to improve reliability for passengers for years to come.

    Story’s work will continue until December and will involve erecting scaffolds over the length of the bridge to carry out structural repair works.

  • Lending a helping hand

    We like doing our bit to keep our worksites and the surrounding areas tidy.

    Chris Burns, Suzanne McKay, Richie Griffiths, and Daniel Haughey (L-R)
    Chris Burns, Suzanne McKay, Richie Griffiths, and Daniel Haughey

    So, while work is ongoing at the Clyde Viaduct, members from Network Rail and Story carried out a litter along the Clyde Walkway.

    The group braved the elements and cleared the walkway and grass verge, each collecting a full bin bag of rubbish that was safely disposed of.

    Litter picking near the Clyde Viaduct back in May 2022
    Litter picking near the Clyde Viaduct back in May 2022
  • Behind the encapsulation

    As we enter July, our £4.7m project to repair the Clyde Viaduct at the Clyde Walkway, Rutherglen, is progressing well. Here is a sneak peek behind the encapsulation on the Viaduct’s first span.

    Behind the encapsulations on the Clyde Viaduct
    Behind the encapsulations on the Clyde Viaduct

    Working with contractor Story, our team has already blasted and primed the steelwork and replaced numerous sections of steel on the underside of the bridge.

    Work is progressing well on the Clyde Viaduct renewal project
    Work is progressing well on the Clyde Viaduct renewal project

    Engineers are now repeating this process on the second span of the bridge. This work requires specialist heavy machinery which means it can be noisy at times but we are doing all that we can to minimise this.

    Our engineers are also waterproofing and repainting the bridge
    Our engineers are also waterproofing and repainting the bridge

    The next main milestone for this project will be the completion of the scaffolding, which is programmed for next week. The bridge has been waterproofed and will be painted and the full project is expected to be completed in December.

Why?

The project is part of a wider programme of maintenance work, designed to keep the rail network safe and reliable for all passengers and freight customers.

Since work started in February, essential repairs and waterproofing to the bridge deck of the viaduct have already taken place.

What will change?

During the second phase of the project, (April onwards) work focuses on repairing and painting the existing steelwork, which involves erecting scaffolding around the viaduct, to allow us to encapsulate it in sheeting and carry out necessary repairs to the underbridge.

The repairs involve the removal and replacement of sections of the steel on the underside of the bridge, work that can only be carried out when no trains are running and means much of this activity is carried out overnight.