Old Kilpatrick: Bridge replacement at A814 Dumbarton Road

Old Kilpatrick: Bridge replacement at A814 Dumbarton Road

Network Rail will demolish and replace the bridge over the railway on A814 Dumbarton Road in Old Kilpatrick from Saturday 17 July until Friday 10 December 2021.

Network Rail will begin work to demolish and replace the bridge over the railway on Dumbarton Road in Old Kilpatrick from Saturday 17 July until Friday 10 December 2021.

The new bridge will strengthen and safeguard the route for the long-term after the deterioration of the old bridge left it unsuitable for the weight and volume of traffic which passes over it daily.

As part of the works, the £1m temporary bailey bridge, which was put in place last year to allow traffic to continue using the route, will also be removed.

Due to the nature of the works, the bridge needs to close to all vehicular traffic from 2 August to 26 November this year to allow the project to be completed safely and efficiently.

Pedestrians will be able to continue using the bridge until 23 August, when it will close completely for demolition and follow-up works, before re-opening on 26 November.

Project Timeline

  1. July 2021: Project begins with compound set-up and de-vegetation works
  2. August 2021: Bridge closes to vehicles and pedestrians until November 2021
  3. October & November 2021: New bridge installed & bridge re-opens to traffic & pedestrians
  4. December 2021: Project complete

Possible Disruptions

  • Saturday 17 July 2021

    Compound set-up which includes installation of temporary offices and welfare facilities for staff; delivery of plant, materials and equipment; installation of fencing and lighting

    The compound will be set up between Dumbarton Road and Great Western Road

  • Saturday 24 July 2021

    Devegetation works, which includes removal of trees and vegetation local to the structure

  • Monday 2 August to Friday 26 November 2021

    Bridge closes to all vehicular traffic but remains open to pedestrians

  • Monday 23 August to Friday 26 November 2021

    Bridge closes to all pedestrians

  • Saturday 4 September to Friday 1 October 2021

    Demolition preparation work including crane pad construction, saw cutting, installation of wingwall scaffolding and overhead line equipment works.

  • Saturday 2 October to Monday 4 October 2021

    Bridge demolition work takes place, which includes the use of power tools and machinery.

    New bridge installation work, which includes the use of crane and heavy plant/machinery

  • Sunday 17 October to Saturday 30 October 2021

    The A82 Southbound on/off slip road will be closed from 14:00 on Sunday 17 October until 23:59 on Saturday 30 October to allow activities, requiring the use of additional plant and personnel, to run concurrently.

  • Saturday 13 November to Friday 26 November 2021

    Surfacing works, which includes the use of plant and machinery

  • Saturday 27 November to Friday 10 December 2021

    Finishing works, which includes the installation of lineside fencing with the use of plant and machinery.

Why?

The existing structure has deteriorated and is no longer fit to hold the weight and volume of traffic which crosses the bridge on a daily basis.

Although we installed a temporary bailey bridge to allow traffic to continue using the route last year, a new permanent bridge needs to be installed, and is now ready.

What will change?

The bailey bridge, which has sat over the existing bridge will be removed and existing the bridge will be demolished.

We will then installed a new permanent bridge, which will strengthen and safeguard the route for both vehicular traffic and pedestrians for the long-term.

Tasks